Comprehensive execution of service stations with a car wash, external networks and roads, training yard and greenery.

Objects made ​​in light frame construction, steel for reinforced concrete foundations. As part of the ongoing work carried out electrical works, water and sewage systems., Ventilation and air conditioning systems, mechanical and electrical heating. The scope of work included the foundation of fuel tanks and LPG gas on a foundation of reinforced concrete.

Usable area: 234 m2 and 488 m2
Volume: 960 m3 and 2771m3
Implementation period: from May 2003 to August 2003 and from October 2003 to December 2003