Repair and modernization of the musical theater audience with the reconstruction of the interior for the new project room acoustics. The scope of work included complete construction and other work, including supply and installation of seats and specially designed acoustic panels of the side walls.

- Inwestor / Investor
- Teatr Muzyczny w Gdyni
- Data rozpoczęcia / Start date
- november 2003
- Data zakończenia / End date
- february 2004
- Kubatura / Cubic capacity
- 6.100 m3
- Powierzchnia / Area
- 555 m2