Waste-Water Treatment Plant in Pszczolki and in Subkowy
Construction of a new wastewater treatment plant for Pszczolki, Rozyny,
Skowarcz, and Kolnik. The investment consisted of a construction and
startup of structures directly involved in the technological process,
such as a grille screen building, a sewage pumping station, a sand
trap, a biofiltration unit and a dispatching unit. Complete
technological networks were also carried out and special technological
measuring equipment was mounted and started up.
Built-up area: 630 m2M
Cubic capacity of buildings: 411 m3
Construction Manager: Lech Palacha
|
|